Simulating the effect of risks on equity return for concession‐based public‐private partnership projects

S. Thomas Ng (Department of Civil Engineering, The University of Hong Kong, Pokfulam, Hong Kong)
Jingzhu Xie (Department of Civil Engineering, The University of Hong Kong, Pokfulam, Hong Kong)
Mohan M. Kumaraswamy (Department of Civil Engineering, The University of Hong Kong, Pokfulam, Hong Kong)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 6 July 2010

1575

Abstract

Purpose

Unlike other project delivery options, a much larger proportion of risks is borne by the private partner in public‐private partnerships, since a large amount of equity is needed to finance the scheme. As a result, it is of paramount importance for the franchisee to analyse the possible project outcomes with due reference to potential risks affecting cash inflow and outflow. The purpose of this paper is to address the shortcomings of deterministic estimations by developing a proposal for a simulation model that aims to unveil the probability distributions of the equity amount and return on equity.

Design/methodology/approach

In this paper, a simulation model is developed to establish the probability distributions of these two indicators under the influence of risks. A simple case study is also presented to illustrate the concept and application of this model.

Findings

The simulation model can generate the probability distributions related to the net present value of the equity component as well as the rate of return on equity.

Practical implications

The method proposed in this paper should help the private investors analyse the amount of equity to be injected to the project and its corresponding return rate.

Originality/value

By referring to the probability distribution, an equity investor can establish whether they can recover their investment and gain a desired return rate. Based upon the risk attitude of the investor, decision‐makers can then decide whether the scheme should be pursued or not.

Keywords

Citation

Ng, S.T., Xie, J. and Kumaraswamy, M.M. (2010), "Simulating the effect of risks on equity return for concession‐based public‐private partnership projects", Engineering, Construction and Architectural Management, Vol. 17 No. 4, pp. 352-368. https://doi.org/10.1108/09699981011056565

Publisher

:

Emerald Group Publishing Limited