Selecting EVM, ESM and EDM(t) for managing construction project schedule

Jyh-Bin Yang (Department of Civil Engineering, National Central University, Taoyuan, Taiwan)
Tzu-Hua Lai (Pacific Engineers & Constructors, Ltd., Taipei, Taiwan)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 16 June 2023

205

Abstract

Purpose

This study aims to review earned value management (EVM)-relative methods, including the original EVM, earned schedule method (ESM) and earned duration management (EDM(t)). This study then proposes a general implementation procedure and some basic principles for the selection of EVM-relative methods.

Design/methodology/approach

After completing an intensive literature review, this study conducts a case study to examine the forecasting performance of project duration using the EVM, ESM and EDM(t) methods.

Findings

When the project is expected to finish on time, ESM with a performance factor equal to 1 is the recommended method. EDM(t) would be the most reliable method during a project's entire lifetime if EDM(t) is expected to be delayed based on past experience.

Research limitations/implications

As this research conducts a case study with only one building construction project, the results might not hold true for all types of construction projects.

Practical implications

EVM, ESM and EDM(t) are simple and data-accessible methods. With the help of a general implementation procedure, applying all three methods would be better. The power of the three methods is definitely larger than that of choosing only one for complex construction projects.

Originality/value

Previous studies have discussed the advantages and disadvantages of EVM, ESM and EDM(t). This study amends the available outcomes. Thus, for schedulers or researchers interested in implementing EVM, ESM and EDM(t), this study can provide more constructive instructions.

Keywords

Acknowledgements

The authors would like to thank the National Science and Technology Council, Taiwan, ROC, for financially supporting this research under Contract No. MOST108-2221-E-008-010-MY3.

Citation

Yang, J.-B. and Lai, T.-H. (2023), "Selecting EVM, ESM and EDM(t) for managing construction project schedule", Engineering, Construction and Architectural Management, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/ECAM-02-2023-0115

Publisher

:

Emerald Publishing Limited

Copyright © 2023, Emerald Publishing Limited