To read this content please select one of the options below:

Sharp schedule compression in urgent emergency construction projects via activity crashing, substitution and overlapping: a case study of Huoshengshan and Leishenshan Hospital projects in Wuhan

Hui Lu (School of Economics and Management, China University of Geosciences, Wuhan, China)
Hongwei Wang (School of Management, Huazhong University of Science and Technology,Wuhan, China)
Dihua Yu (China Construction Third Engineering Bureau Group Co., Ltd., Wuhan, China)
Jian Ye (China Construction Third Engineering Bureau Group Co., Ltd., Wuhan, China)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 1 February 2022

Issue publication date: 1 September 2023

638

Abstract

Purpose

To meet the rapidly increasing demand for medical treatment during the outbreak of COVID-19, Huoshengshan and Leishenshan Hospital are rapidly built (9–12 days) in Wuhan. These two urgent emergency projects are unprecedented. In general, substantial literature suggests that the possibility of shortening a schedule by more than a quarter of its original duration is implausible. By contrast, the two projects had successfully compressed the schedules from months and years to about ten days. This study aims to investigate how this was done and provide references for future projects.

Design/methodology/approach

The study uses qualitative case study techniques to analyze the project practices in two urgent emergency projects. Data were gathered through semi-structured interviews and archival research. During interviews, interviewees were asked to describe the project practices adopted to overcome the challenges and freely share their experiences and knowledge.

Findings

The results illustrate that a high degree of schedule compression is achievable through tactful crashing, substitution and overlapping applications. The successful practices heavily rely on the high capacity of participants and necessary organization, management and technology innovations, such as three-level matrix organizational structure, reverse design method, site partition, mock-up room first strategies and prefabricated construction technology. For instance, the reverse design method is one of the most significant innovations to project simplification and accelerate and worthy of promotion for future emergency projects.

Practical implications

The empirical findings are significant as they evoke new thinking and direction for addressing the main challenges of sharp schedule compression and provide valuable references for future emergency projects, including selecting high-capacity contractors and replacing the conventional design methods with reverse design.

Originality/value

Substantial studies indicate that the maximum degree of schedule compression is highly unlikely to exceed 25%, but this study suggests that sharp compression is possible. Although with flaws in its beauty (i.e. compressing schedule at the expense of construction cost and quality), it is also a breakthrough. It provides the building block for future research in this fertile and unexplored area.

Keywords

Acknowledgements

This study is supported in part by the National Natural Science Foundation of China under Grant (Nos. 72042015, 72001195, and 71821001), the National Social Science Fund of China (No. 21AZD074), and the Fundamental Research Funds for the Central Universities, China University of Geosciences (Wuhan) (No. 2019109). The authors would like to thank the GC and other participants for providing valuable information for this study.

Citation

Lu, H., Wang, H., Yu, D. and Ye, J. (2023), "Sharp schedule compression in urgent emergency construction projects via activity crashing, substitution and overlapping: a case study of Huoshengshan and Leishenshan Hospital projects in Wuhan", Engineering, Construction and Architectural Management, Vol. 30 No. 8, pp. 3696-3712. https://doi.org/10.1108/ECAM-07-2021-0654

Publisher

:

Emerald Publishing Limited

Copyright © 2022, Emerald Publishing Limited

Related articles