Resource budget for workface planning in industrial-construction

Ming Fung Francis Siu (Department of Building and Real Estate, Hong Kong Polytechnic University, Kowloon, Hong Kong)

Facilities

ISSN: 0263-2772

Article publication date: 26 February 2019

Issue publication date: 8 March 2019

548

Abstract

Purpose

The purpose of this paper is to develop a novel analytical approach for workface planning practice in industrial-construction sector such that the construction work package (CWP) resource budget can be sufficiently planned for delivering possible field installation work package (FIWP) schedules with work uncertainty.

Design/methodology/approach

The relationship between CWP resource budget and FIWP schedules is first elucidated based on workface planning practice. The literature of work packaging, workface planning and project scheduling is reviewed. A novel analytical approach is then developed to quantify CWP resource budget based on a probability theory, in consideration of the probability of occurrence of feasible FIWP schedules formulated based on a resource scheduling approach. The results of case studies given by the new approach are cross validated by using simulation and optimization techniques.

Findings

The new analytical approach can assist workface planning by quantifying the expected CWP resource budget to deliver the FIWP work scope with certain activities that are planned at project level and with uncertain activities that are found at workface level.

Practical implications

The new analytical approach helps project and workface planners to reliably deploy CWP resource budget for delivering FIWP schedules instead of guessing the budget based on experience. An industrial-construction project for upgrading oil-sands refinery facility is used to show the practical implications.

Originality/value

This research develops a new analytical approach for workface planning practice to determine sufficient CWP resource budget for delivering feasible FIWP schedules with work uncertainty.

Keywords

Acknowledgements

The author would like to acknowledge Tidder, V., Lu, M., and AbouRizk, S. for sharing their knowledge of managing industrial-construction facility using workface planning technique, and providing a testbed of upgrading industrial plant facility to implement the proposed analytical approach. This work was supported by the National Science and Engineering Research Council (NSERC) under Industrial Research Chair Program [IRCPJ #195558-10].

Citation

Siu, M.F.F. (2019), "Resource budget for workface planning in industrial-construction", Facilities, Vol. 37 No. 5/6, pp. 292-312. https://doi.org/10.1108/F-04-2018-0057

Publisher

:

Emerald Publishing Limited

Copyright © 2019, Emerald Publishing Limited

Related articles