Adapting to COVID-19 on construction sites: what are the lessons for long-term improvements in safety and worker effectiveness?

Wendy Jones (School of Architecture, Building and Civil Engineering, Loughborough University, Loughborough, UK)
Alistair G.F. Gibb (School of Architecture, Building and Civil Engineering, Loughborough University, Loughborough, UK)
Vivien Chow (School of Architecture, Building and Civil Engineering, Loughborough University, Loughborough, UK)

Journal of Engineering, Design and Technology

ISSN: 1726-0531

Article publication date: 11 August 2021

Issue publication date: 3 January 2022

999

Abstract

Purpose

Substantial changes were made on many UK construction projects in response to the COVID-19 pandemic. The purpose of this paper is to explore the unanticipated positive consequences of these and the scope for longer-term learning and developments within the sector.

Design/methodology/approach

A qualitative approach was used, semi-structured interviews were conducted across six major project sites. Interviewees (n = 33) included site and senior managers, supply chain representatives and occupational safety and health (OSH) professionals. The interviews explored their experiences of working on site during the pandemic, the changes made to work practices and their perceived impacts of these changes.

Findings

Improved planning and work sequencing were part of the revised process to make sites COVID-secure. This increased worker effectiveness and housekeeping/tidiness. The view on some sites was that this would improve OSH performance. The changes were perceived to be beneficial but may not be accepted by clients in the long term, as they could result in projects taking longer to complete. The ways in which COVID-19 risk has been communicated and perceived also provides longer-term lessons for the sector’s OSH management and training.

Originality/value

Construction has adapted rapidly and effectively to new ways of working during the pandemic. This research captured in real time some of the changes made and presents an argument for embedding and adopting the changes to improve working arrangements and OSH within the construction sector.

Keywords

Acknowledgements

This research was commissioned by the following companies, who also facilitated access to interviewees from their own organisations and their supply chain. These contributions are appreciated. Balfour Beatty; GKR Scaffolding Limited; Kier Group; Mace Group; Morgan Sindall Group; Skanska UK.

This report was funded by Balfour Beatty, Mace, Skanska, Kier, Morgan Sindall, GK Scaffolding.

Citation

Jones, W., Gibb, A.G.F. and Chow, V. (2022), "Adapting to COVID-19 on construction sites: what are the lessons for long-term improvements in safety and worker effectiveness?", Journal of Engineering, Design and Technology, Vol. 20 No. 1, pp. 66-85. https://doi.org/10.1108/JEDT-11-2020-0473

Publisher

:

Emerald Publishing Limited

Copyright © 2021, Emerald Publishing Limited