A new framework for time-cost trade-off considering float loss impact

Sameh Monir El-Sayegh (Department of Civil Engineering, American University of Sharjah, Sharjah, United Arab Emirates)
Rana Al-Haj (Department of Civil Engineering, American University of Sharjah, Sharjah, United Arab Emirates)

Journal of Financial Management of Property and Construction

ISSN: 1366-4387

Article publication date: 3 April 2017

343

Abstract

Purpose

The purpose of this paper is to propose a new framework for time–cost trade-off. The new framework provides the optimum time–cost value taking into account the float loss impact.

Design/methodology/approach

The stochastic framework uses Monte Carlo Simulation to calculate the effect of float loss on risk. This is later translated into an added cost to the trade-off problem. Five examples, from literature, are solved using the proposed framework to test the applicability of the developed framework.

Findings

The results confirmed the research hypothesis that the new optimum solution will be at a higher duration and cost but at a lower risk compared to traditional methods. The probabilities of finishing the project on time using the developed framework in all five cases were better than those using the classical deterministic optimization technique.

Originality/value

The objective of time–cost trade-off is to determine the optimum project duration corresponding to the minimum total cost. Time–cost trade-off techniques result in reducing the available float for noncritical activities and thus increasing the schedule risks. Existing deterministic optimization technique does not consider the impact of the float loss within the noncritical activities when the project duration is being crashed. The new framework allows project managers to exercise new trade-offs between time, cost and risk which will ultimately improve the chances of achieving project objectives.

Keywords

Citation

El-Sayegh, S.M. and Al-Haj, R. (2017), "A new framework for time-cost trade-off considering float loss impact", Journal of Financial Management of Property and Construction, Vol. 22 No. 1, pp. 20-36. https://doi.org/10.1108/JFMPC-02-2016-0007

Publisher

:

Emerald Publishing Limited

Copyright © 2017, Emerald Publishing Limited

Related articles