Underlying causes and mitigation measures of delays in construction projects: An empirical study

Amílcar Arantes (Civil Engineering, Architecture and Georesources, Universidade de Lisboa Instituto de Investigacao e Inovacao em Engenharia Civil para a Sustentabilidade, Lisboa, Portugal)
Luís Miguel D.F. Ferreira (Department of Mechanical Engineering, University of Coimbra, Coimbra, Portugal)

Journal of Financial Management of Property and Construction

ISSN: 1366-4387

Article publication date: 25 February 2020

Issue publication date: 16 July 2020

1585

Abstract

Purpose

The purpose of this study is to contribute to the theory and practice of project management in the construction industry by identifying the primary causes and extracting the underlying causes of construction delays and providing recommendations on delay mitigation measures.

Design/methodology/approach

AA survey was used to identify the importance of 47 causes of delays. The relative importance index was used to rank them, factor analysis was applied to extract the underlying causes and focus group interviews were used for discussion and development of mitigation measures.

Findings

Six of the ten most important causes are in the top ten universal delays in construction projects. Factor analysis revealed six underlying causes: improper planning, poor consultant performance, inefficient site management, owner influence, bureaucracy and sub-standard contracts.

Practical implications

The owner/sponsor/client must have adequate engineering and project management skills to be able to evaluate proposals and contractors more accurately, economically and technically. The bidding and contract award process should focus on the most economically advantageous proposal and contracts should provide for mechanisms for managing risks while executing projects. Contractors should select reliable, high-quality subcontractors and suppliers and should have competent site managers.

Originality/value

This work expands and improves the understanding of the causes of delays in construction projects by providing an empirical study of the causes of delays and respective mitigation measures in Portugal.

Keywords

Citation

Arantes, A. and Ferreira, L.M.D.F. (2020), "Underlying causes and mitigation measures of delays in construction projects: An empirical study", Journal of Financial Management of Property and Construction, Vol. 25 No. 2, pp. 165-181. https://doi.org/10.1108/JFMPC-03-2019-0029

Publisher

:

Emerald Publishing Limited

Copyright © 2020, Emerald Publishing Limited