A three-stage solution approach with a repeated-negotiation mechanism for the decentralized resource-constrained multi-project scheduling problem

Hongri Mao (School of Traffic and Transportation Engineering, Changsha University of Science and Technology, Changsha, China)
Jianbo Yuan (School of Traffic and Transportation Engineering, Changsha University of Science and Technology, Changsha, China)

Kybernetes

ISSN: 0368-492X

Article publication date: 8 March 2024

18

Abstract

Purpose

This study develops a model and algorithm to solve the decentralized resource-constrained multi-project scheduling problem (DRCMPSP) and provides a suitable priority rule (PR) for coordinating global resource conflicts among multiple projects.

Design/methodology/approach

This study addresses the DRCMPSP, which respects the information privacy requirements of project agents; that is, there is no single manager centrally in charge of generating multi-project scheduling. Accordingly, a three-stage model was proposed for the decentralized management of multiple projects. To solve this model, a three-stage solution approach with a repeated negotiation mechanism was proposed.

Findings

The experimental results obtained using the Multi-Project Scheduling Problem LIBrary confirm that our approach outperforms existing methods, regardless of the average utilization factor (AUF). Comparative analysis revealed that delaying activities in the lower project makespan produces a lower average project delay. Furthermore, the new PR LMS performed better in problem subsets with AUF < 1 and large-scale subsets with AUF > 1.

Originality/value

A solution approach with a repeated-negotiation mechanism suitable for the DRCMPSP and a new PR for coordinating global resource allocation are proposed.

Keywords

Acknowledgements

This document is the results of the research project funded by the National Natural Science Foundation of China (grant number 51578080), Science and Technology Progress and Innovation Project of Department of transportation of Hunan province (grant number 202039), and Research and Innovation Project for Graduate Students in Hunan Province, China (grant number CX20200826).

Citation

Mao, H. and Yuan, J. (2024), "A three-stage solution approach with a repeated-negotiation mechanism for the decentralized resource-constrained multi-project scheduling problem", Kybernetes, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/K-09-2023-1763

Publisher

:

Emerald Publishing Limited

Copyright © 2024, Emerald Publishing Limited

Related articles