Improving accuracy of conceptual cost estimation using MRA and ANFIS in Indonesian building projects

Dwifitra Jumas (Quantity Surveying, Faculty of Built Environment, University of Malaya, Kuala Lumpur, Malaysia) (Quantity Surveying, Universitas Bung Hatta, Padang, Indonesia)
Faizul Azli Mohd-Rahim (Quantity Surveying, Faculty of Built Environment, University of Malaya, Kuala Lumpur, Malaysia)
Nurshuhada Zainon (Quantity Surveying, Faculty of Built Environment, University of Malaya, Kuala Lumpur, Malaysia)
Wayudi P. Utama (Quantity Surveying, Universitas Bung Hatta, Padang, Indonesia)

Built Environment Project and Asset Management

ISSN: 2044-124X

Article publication date: 11 July 2018

Issue publication date: 14 September 2018

316

Abstract

Purpose

The purpose of this paper is to develop a conceptual cost estimation (CCE) model for building project by using a pragmatic approach, which is a mix of tools drawn from multiple regression analysis (MRA) and adaptive neuro-fuzzy inference system (ANFIS), to improve the accuracy of cost estimation at an early stage.

Design/methodology/approach

This paper presents a set of MRA and integrating MRA with ANFIS or MRANFIS. A simultaneous regression analysis was developed to determine the main cost factors from 12 variables as input variables in the ANFIS model. Cost data from 78 projects of state building in West Sumatra, Indonesia were used to indicate the advantages of the proposed model.

Findings

The result shows that the proposed model, MRANFIS, has successfully improved the mean absolute percent error (MAPE) by 2.8 percent from MRA of 10.7–7.9 percent for closeness of fit to the model data and by 3.1 percent from MRA of 9.8–6.7 percent for prediction performance to the new data.

Research limitations/implications

Because the significant variables are different for each building type, the model may be not appropriate for other buildings depending on the characteristics of building. The models can be used and analyzed based on the own historical project data for each case so that the model can be applied.

Originality/value

The study thus provides better accuracy of CCE at an early stage for state building projects in West Sumatra, Indonesia by using the integrated model of MRA and ANFIS.

Keywords

Citation

Jumas, D., Mohd-Rahim, F.A., Zainon, N. and Utama, W.P. (2018), "Improving accuracy of conceptual cost estimation using MRA and ANFIS in Indonesian building projects", Built Environment Project and Asset Management, Vol. 8 No. 4, pp. 348-357. https://doi.org/10.1108/BEPAM-11-2017-0111