A project control process in pre‐construction phases: Focus on effective methodology

Khaled Al‐Reshaid (Department of Civil Engineering and Kuwait University Construction Program, Kuwait University, Safat, Kuwait)
Nabil Kartam (Department of Civil Engineering and Kuwait University Construction Program, Kuwait University, Safat, Kuwait)
Narendra Tewari (Department of Civil Engineering and Kuwait University Construction Program, Kuwait University, Safat, Kuwait)
Haya Al‐Bader (Department of Civil Engineering and Kuwait University Construction Program, Kuwait University, Safat, Kuwait)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 1 August 2005

5287

Abstract

Purpose

It is a well‐known fact that the construction industry always passes through two distinctive problems during the construction stage: slippages of project‐schedules, i.e. time‐frame, and overruns of project‐costs, i.e. budget. However, limited literature is available to solve or dilute these two problems before they even occur. It is strongly believed that the bulk of the two mentioned problems can be mitigated to a great extent, if not eliminated, provided that proper attention is paid to the pre‐construction phases of projects. Normally projects are implemented through traditionally old techniques which generally emphasize only solving “construction problems during the construction phase”. The aim of this article is therefore to unveil a professional methodology known as Project Control System (PCS) focusing on pre‐construction phases of construction projects.

Design/methodology/approach

In this article, the authors share the lessons learned during implementation of Kuwait University projects worth approximately $400 million in a span of ten years. The task of the project management/construction management (PM/CM) is being provided to the university by a joint venture team of international and local specialists.

Findings

The pre‐construction methodology ensures smooth and successful implementation during construction phases of the projects as they are generally executed in a fast‐pace, deadline‐driven and cost‐conscious environment. The intuitive proactive methods, if implemented during pre‐construction stage, automatically answer the questions that are encountered during the execution periods of projects.

Originality/value

In this article, the authors share the lessons learned during PM/CM during projects over a span of ten years, which could be of use to others.

Keywords

Citation

Al‐Reshaid, K., Kartam, N., Tewari, N. and Al‐Bader, H. (2005), "A project control process in pre‐construction phases: Focus on effective methodology", Engineering, Construction and Architectural Management, Vol. 12 No. 4, pp. 351-372. https://doi.org/10.1108/09699980510608811