Project schedule compression: a multi-objective methodology

Osama Moselhi (Concordia University, Montreal, Canada)
Nazila Roofigari-Esfahan (Department of Civil Engineering, McMaster University, Hamilton, Canada)

Construction Innovation

ISSN: 1471-4175

Article publication date: 7 October 2013

1982

Abstract

Purpose

This paper aims to present a new method to circumvent the limitations of current schedule compression methods which reduce schedule crashing to the traditional time-cost trade-off analysis, where only cost is considered.

Design/methodology/approach

The schedule compression process is modeled as a multi-attributed decision making problem in which different factors contribute to priority setting for activity crashing. For this purpose, a modified format of the Multiple Binary Decision Method (MBDM) along with iterative crashing process is utilized. The method is implemented in MATLAB, with a dynamic link to MS-Project to facilitate the needed iterative rescheduling. To demonstrate the use of the developed method and to present its capabilities, a numerical example drawn from literature was analysed.

Findings

When considering cost only, the generated results were in good agreement with those generated using the harmony search (HS) method, particularly in capturing the project least-cost duration. However, when other factors in addition to cost were considered, as expected, different project least-cost and associated durations were obtained.

Research limitations/implications

The developed method is not applicable, in its present formulation, to what is known as “linear projects” such as construction of highways and pipeline infrastructure projects which exhibit high degree of repetitive construction.

Originality/value

The novelty of the developed method lies in its capacity to allow for the consideration of a number of factors in addition to cost in performing schedule compression. Also through its allowance for possible variations in the relative importance of these factors at the individual activity level, it provides contractors with flexibility to consider a number of compression execution plans and identifies the most suitable plan. Accordingly, it enables the integration of contractors' judgment and experience in the crashing process and permits consideration of different project environments and constraints.

Keywords

Citation

Moselhi, O. and Roofigari-Esfahan, N. (2013), "Project schedule compression: a multi-objective methodology", Construction Innovation, Vol. 13 No. 4, pp. 374-393. https://doi.org/10.1108/CI-03-2011-0010