Evaluating construction delays using productivity-based resource reallocation for economic feasibility
Engineering, Construction and Architectural Management
ISSN: 0969-9988
Article publication date: 1 February 2022
Issue publication date: 8 May 2023
Abstract
Purpose
Work crew productivity and the application of limited resources are necessary elements in construction duration delay analysis. This study thus proposes a method to analyze construction delays and resource reallocation based on work crew productivity and resource constraints. The study also presents an economic feasibility analysis that maximizes economic effect by reducing construction duration, the cost of resource reallocation, delay liquidated damages (DLDs) and incentives for reducing contractual duration.
Design/methodology/approach
The proposed method involved three steps. First, work crew characteristics such as productivity, unit price and workload helped analyze delay information, including delay duration, reducible duration and daily reduced cost. Next, a goal programming method assessed resource reallocation based on the priority (as determined by decision-makers) of each constraint condition, such as the available number of workers, cost, goal workload and statutory working hours. Lastly, the level of reallocation was analyzed based on the results of the economic feasibility analysis and decision-makers’ delay attitudes.
Findings
A case study was performed to test the proposed method's applicability. Its involved sensitivity analysis indicated proposing to decision-makers a scenario based on the prioritization of economic feasibility. The proposed method's applicability proved high for decision-makers, as they can determine whether to reduce construction duration per the proposed data.
Originality/value
The proposed method's main contribution is the reallocation of resources to reduce construction duration based on work crew productivity and the prioritization of limited resources. The proposed method can analyze the differences in productivity between the plan and actual progress, as well as calculate the necessary number of workers. Decision-makers can then reduce the appropriate level of contractual duration based on their own delay attitude, constraint condition prioritization and results from daily economic feasibility analyses.
Keywords
Citation
Lee, C. (2023), "Evaluating construction delays using productivity-based resource reallocation for economic feasibility", Engineering, Construction and Architectural Management, Vol. 30 No. 4, pp. 1679-1696. https://doi.org/10.1108/ECAM-09-2019-0503
Publisher
:Emerald Publishing Limited
Copyright © 2022, Emerald Publishing Limited