Modelling critical success factors (CSFs) for Ghanaian public–private partnership (PPP) power projects using fuzzy synthetic evaluation (FSE)

Augustine Senanu Komla Kukah (Department of Construction Technology and Management, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
De-Graft Owusu-Manu (Department of Construction Technology and Management, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
Edward Badu (Department of Construction Technology and Management, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
David John Edwards (Department of the Built Environment, Birmingham City University, Birmingham, UK and Faculty of Engineering and the Built Environment, Doornfontein Campus, University of Johannesburg, Johannesburg, South Africa)
Eric Asamoah (Department of Statistics and Actuarial Science, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)

Journal of Facilities Management

ISSN: 1472-5967

Article publication date: 10 July 2023

96

Abstract

Purpose

The purpose of this paper was to first identify and then model the impact of critical success factors (CSFs) of public–private partnership (PPP) power projects.

Design/methodology/approach

Review of empirical literature came out with 20 CSFs which were ranked by experts and industry practitioners through a two-round Delphi questionnaire survey.

Findings

These CSFs were grouped into CSF groups (CSFGs) using component analysis, and they served as the input variables for fuzzy analysis. The six components were collaboration and transparency, guarantee and permits, socio-political support, expected profitability, technical feasibility and risk allocation (RA). Overall success index of PPP power projects in Ghana was 5.966 and showed there is high impact of CSFGs on project success. Fuzzy analysis also confirmed RA as the most significant CSFG.

Originality/value

The model developed can serve as a multi-dimension CSF framework that can be used as a success attainment tool for PPP power projects. For policy developers and stakeholders, the model serves as a pointer to issues which the government/public sector must focus on to attract huge investments from the private sector in the power sector.

Keywords

Citation

Kukah, A.S.K., Owusu-Manu, D.-G., Badu, E., Edwards, D.J. and Asamoah, E. (2023), "Modelling critical success factors (CSFs) for Ghanaian public–private partnership (PPP) power projects using fuzzy synthetic evaluation (FSE)", Journal of Facilities Management, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/JFM-08-2022-0096

Publisher

:

Emerald Publishing Limited

Copyright © 2023, Emerald Publishing Limited

Related articles