Prelims
ISBN: 978-1-78714-830-7, eISBN: 978-1-78714-829-1
Publication date: 10 October 2017
Citation
Mikkelsen, H. and Riis, J.O. (2017), "Prelims", Project Management, Emerald Publishing Limited, Leeds, pp. i-xxvi. https://doi.org/10.1108/978-1-78714-829-120171015
Publisher
:Emerald Publishing Limited
Copyright © 2017 Emerald Publishing Limited
Half Title Page
PROJECT MANAGEMENT
A Multi-Perspective Leadership Framework
Title Page
PROJECT MANAGEMENT
A Multi-Perspective Leadership Framework
BY
HANS MIKKELSEN
PRODEVO Consulting, Aalborg University, Denmark
JENS O. RIIS
Aalborg University, Denmark
United Kingdom – North America – Japan – India – Malaysia – China
Copyright Page
Emerald Publishing Limited
Howard House, Wagon Lane, Bingley BD16 1WA, UK
First edition 2017
Copyright © 2017 Emerald Publishing Limited
Reprints and permissions service
Contact: permissions@emeraldinsight.com
No part of this book may be reproduced, stored in a retrieval system, transmitted in any form or by any means electronic, mechanical, photocopying, recording or otherwise without either the prior written permission of the publisher or a licence permitting restricted copying issued in the UK by The Copyright Licensing Agency and in the USA by The Copyright Clearance Center. Any opinions expressed in the chapters are those of the authors. Whilst Emerald makes every effort to ensure the quality and accuracy of its content, Emerald makes no representation implied or otherwise, as to the chapters’ suitability and application and disclaims any warranties, express or implied, to their use.
British Library Cataloguing in Publication Data
A catalogue record for this book is available from the British Library
ISBN: 978-1-78714-830-7 (Print)
ISBN: 978-1-78714-829-1 (Online)
ISBN: 978-1-78743-266-6 (Epub)
List of Figures
Chapter 1 | ||
Figure 1.1 | The Five-by-Five Project Management Model. | 7 |
Figure 1.2 | The Planning Process is Circular. | 14 |
Figure 1.3 | Four Complementary Perspectives. | 28 |
Figure 1.4 | Narrow and Broad Visions. | 31 |
Figure 1.5 | Three Types of Relationships between a Project and Organizational Change. | 43 |
Figure 1.6 | The Total Elapsed Change Process. | 44 |
Chapter 2 | ||
Figure 2.1 | The PPSOP Model. | 62 |
Figure 2.2 | Consequences of Uncertainty. | 68 |
Figure 2.3 | Dimensions of Complexity. | 70 |
Figure 2.4 | Forming the Project Based on Synergy Considerations. | 75 |
Figure 2.5 | Aspects of Forming a Project. | 77 |
Chapter 3 | ||
Figure 3.1 | Structuring a Project as a Combination of Work Paths and Time. | 90 |
Figure 3.2 | A Cascade Model of a Production Group Project. | 94 |
Figure 3.3 | Project Processes. | 96 |
Figure 3.4 | Four Tasks of the Change Process. | 100 |
Figure 3.5 | Resistance to Change. | 103 |
Figure 3.6 | Driving Forces of Change. | 104 |
Figure 3.7 | The Choice of Course of Action is Determined by the Project Complexity. | 110 |
Figure 3.8 | Some Detailed Check Points Concerning the Course of Action. | 111 |
Figure 3.9 | Four Approaches to Planning the Course of a Project. | 115 |
Figure 3.10 | Decisions During the Project. | 116 |
Figure 3.11 | Kotter’s Eight Points in a Change Process. | 123 |
Figure 3.12 | A Model of Project Planning. | 126 |
Figure 3.13 | Planning Events During the Project. | 127 |
Figure 3.14 | Aspects of Preparing a Master Plan for the Course of Action. | 128 |
Figure 3.15 | A Typical Life Cycle for a Renewal Project. | 130 |
Figure 3.16 | The Dilemma of Project Planning. | 132 |
Figure 3.17 | Seven Principles of Agilean Thinking for Project Management. | 141 |
Chapter 4 | ||
Figure 4.1 | An Example of a Typical Project Organization. | 150 |
Figure 4.2 | A Basic Pattern of a Project Organization. | 152 |
Figure 4.3 | Participation versus Influence. | 178 |
Figure 4.4 | An Example of a Project Organization Diagram. | 180 |
Figure 4.5 | Two Organizational Forms and Work Culture. | 187 |
Figure 4.6 | The Project Organization as an Arena for Cooperation with Other Organizational Units. | 192 |
Figure 4.7 | An Example of Values in Partnering. | 195 |
Chapter 5 | ||
Figure 5.1 | Aspects of Project Teamwork. | 203 |
Figure 5.2 | The Special Characteristics of Project Groups. | 204 |
Figure 5.3 | Examples of Inappropriate Group Culture. | 205 |
Figure 5.4 | The 5C Model. | 208 |
Figure 5.5 | Work Patterns for Project Groups. | 210 |
Figure 5.6 | Types of Project Cooperation. | 213 |
Figure 5.7 | Project Work Needs Three Rooms. | 218 |
Figure 5.8 | Intensive Work Patterns. | 219 |
Figure 5.9 | Energy Creators and Energy Killers in Project Work. | 221 |
Figure 5.10 | Two Problem-Solving Processes. | 231 |
Figure 5.11 | Elevator Model. | 235 |
Figure 5.12 | Field of Tensions. | 238 |
Figure 5.13 | Stages of Group Development. | 243 |
Figure 5.14 | Four Kinds of Learning. | 248 |
Chapter 6 | ||
Figure 6.1 | What Kind of a Project Manager Are You? | 255 |
Figure 6.2 | The Special Characteristics of a Project Management. | 256 |
Figure 6.3 | Five Project Management Areas. | 258 |
Figure 6.4 | The Project Manager and Creation of Results. | 259 |
Figure 6.5 | The Project Coordination Tasks. | 261 |
Figure 6.6 | Differences between Leadership and Control. | 262 |
Figure 6.7 | Conditions for Project Management. | 267 |
Figure 6.8 | Some Requirements for Project Managers of Tomorrow. | 269 |
Figure 6.9 | Adapt Leadership Style to Project Phases. | 270 |
Chapter 7 | ||
Figure 7.1 | Five-by-Five Project Control Model. | 284 |
Figure 7.2 | Project Control Is Determined by the Complexity. | 287 |
Figure 7.3 | Effect Areas of Control Decisions. | 289 |
Figure 7.4 | The Good Activity Control. | 291 |
Figure 7.5 | Forward-Oriented Follow-up. | 294 |
Figure 7.6 | General Control Model – Control Loops. | 294 |
Figure 7.7 | Aspects of Managing Complex Projects. | 298 |
Figure 7.8 | Elements in Evaluation of a Completed Project. | 301 |
Figure 7.9 | Considering Imposed Effects. | 307 |
Figure 7.10 | Life Cycle Cost Model. | 309 |
Figure 7.11 | Elements of Quality Assurance. | 311 |
Figure 7.12 | Quality via People versus Quality via Methods. | 311 |
Figure 7.13 | Planning Levels. | 313 |
Figure 7.14 | Effects of Delay and Cost Budget Overrun. | 317 |
Figure 7.15 | Economy Control Tasks. | 323 |
Figure 7.16 | Life-cycle Economy. | 324 |
Figure 7.17 | Project Costs. | 326 |
Chapter 8 | ||
Figure 8.1 | The Gray Zone of Company Development Initiatives In-between Major Strategic Efforts and Projects in Single Sections. | 338 |
Figure 8.2 | Many Development Initiatives Need to Be Formed to Ensure Value-adding. | 340 |
Figure 8.3 | Means of Connecting Strategy and Development Projects. | 343 |
Figure 8.4 | Internal Development Takes Place at Several Levels. | 350 |
Figure 8.5 | An Example of a Diagram of Balances in a Portfolio. | 352 |
Figure 8.6 | Examples of Dimensions of Balancing Two Portfolios. | 352 |
Figure 8.7 | Orchestration Forms. | 357 |
Figure 8.8 | From Ideas to Portfolio. | 358 |
Figure 8.9 | The Attention of the Portfolio Management Should Be Directed Toward Value Creation. | 358 |
Figure 8.10 | Classical Tasks of Portfolio Management. | 359 |
Figure 8.11 | Definition of a Program. | 360 |
Figure 8.12 | An Example of an Overall Milestone Plan for a Program of a Total Relocation of a Production Plant. | 362 |
Figure 8.13 | The Transformation Matrix. | 364 |
Figure 8.14 | Transformation from Strategy into Initiatives in a Strategic Effort Area: Sales of Process Equipment “M1” in Northern Europe. | 365 |
Figure 8.15 | Focus on the Value of Projects. | 368 |
Figure 8.16 | A Model of Functions for Program Management. | 369 |
Figure 8.17 | Important Information Sheets for Program Management. | 370 |
Figure 8.18 | Elements of Agile Company Development. | 374 |
Chapter 9 | ||
Figure 9.1 | Different Relationships Between a Renewal Project and Change. | 394 |
Figure 9.2 | The Total Change Process. | 395 |
Figure 9.3 | Roles of the Change Organization Compared to Roles of the Project Organization. | 397 |
Figure 9.4 | Tasks of the Change Manager. | 398 |
Figure 9.5 | The Context of Company Development. | 400 |
Figure 9.6 | The Management Triad. | 401 |
Appendix A | ||
Figure A1 | Four Pictures. | 417 |
Figure A2 | A Frame for the Portrait. | 419 |
Figure A3 | Examples of Project Portraits. | 419 |
Appendix B | ||
Figure B1 | Challenges As a Basis for Planning. | 428 |
Figure B2 | Description of Project Complexity. | 430 |
Figure B3 | Examples of Project Conditions. | 431 |
Figure B4 | Analysis and Prioritization of Challenges – An Example. | 431 |
Figure B5 | Points of Special Attention. | 432 |
Figure B6 | The Coalition Model. | 434 |
Figure B7 | Form: Analysis of Interested Parties (Stakeholders). | 438 |
Figure B8 | Interested Parties’ Position. | 439 |
Figure B9 | Classification of Interested Parties. | 440 |
Figure B10 | Sociogram. | 441 |
Figure B11 | Connections Between Project Goals. | 443 |
Figure B12 | Types of Benefit Goals. | 445 |
Figure B13 | Value Calculation. | 450 |
Figure B14 | A Business Case. | 451 |
Figure B15 | Goals and Means Are Linked. | 452 |
Figure B16 | Concept Documentation. | 454 |
Figure B17 | Form for Analysis of Uncertainties. | 458 |
Figure B18 | Analysis of Milestones and Activities. | 459 |
Figure B19 | Sorting Uncertainties. | 460 |
Figure B20 | Interfaces and Connections. | 462 |
Figure B21 | SWOT Analysis. | 463 |
Figure B22 | RPD Example (a) and (b). | 465 |
Figure B23 | Decision Tree Example. | 466 |
Appendix C | ||
Figure C1 | Planning Points in the Project Process. | 470 |
Figure C2 | Planning Model. | 472 |
Figure C3 | Purpose of the Picture of Interested Parties. | 477 |
Figure C4 | Pictures of the Project Environment. | 479 |
Figure C5 | Five-by-Five Model of Control Functions. | 489 |
Figure C6 | Structure for Development of a Manufacturing System. | 497 |
Figure C7 | Process Diagram Is the Basis for Structure (an Example). | 499 |
Figure C8 | A Process Plant Is Divided into Modules/Units (a Cement Factory). | 500 |
Figure C9 | An Example of Project Structure. | 501 |
Figure C10 | Three Structures and Their Connections. | 502 |
Figure C11 | Activity Relations to Project Structure. | 502 |
Figure C12 | Different Activity Delimitations. | 503 |
Figure C13 | The Classic Phase Model – The Waterfall Model. | 505 |
Figure C14 | A Phase Model for an IT Project. | 506 |
Figure C15 | A Phase Model for Implementation of a Standard IT System. | 506 |
Figure C16 | A Phase Model for a Product Development Project. | 507 |
Figure C17 | A Phase Model for Medicare Product Development. | 507 |
Figure C18 | Phases in an Engineering/Construction Project. | 508 |
Figure C19 | A Phase Model for a Building Project. | 508 |
Figure C20 | The Concept-Based Approach Model. | 509 |
Figure C21 | A Three-Stream Model for Integrated Product Development. | 519 |
Figure C22 | A Four-Stream Model for Development of a Production System. | 520 |
Figure C23 | Streams in a Technical Project. | 520 |
Figure C24 | The Principle of an Iterative Approach. | 523 |
Figure C25 | An Example of an Iterative Approach. | 524 |
Figure C26 | Different Views – Different Phases. | 525 |
Figure C27 | Organizational Conditions for the Project. | 526 |
Figure C28 | Interested Parties’ Understanding and Acceptance of Necessity or Value. | 527 |
Figure C29 | Interested Parties’ Understanding and Acceptance of the Concept and Vision. | 528 |
Figure C30 | Interested Parties’ Change Competency. | 528 |
Figure C31 | Change Analysis and the Change Task. | 531 |
Figure C32 | Means of Creating Engagement. | 532 |
Figure C33 | Considerations from interested parties. | 533 |
Figure C34 | Structure of the Coordination and Control Schedule. | 536 |
Figure C35 | Factors Determining Activity Duration. | 542 |
Figure C36 | The Active Project Start. | 553 |
Appendix D | ||
Figure D1 | Basic Pattern of the Project Organization. | 579 |
Figure D2 | The Project Team Structure Is Related to the Work Paths. | 580 |
Figure D3 | Organogram with Contact Lines. | 582 |
Figure D4 | Responsibility Chart. | 584 |
Figure D5 | Two Examples of Interaction. | 591 |
Figure D6 | Example: Matrix Organization in a Technical Manufacturing Company. | 592 |
Figure D7 | Example: Matrix Organization in a New Product Development Department. | 593 |
Appendix E | ||
Figure E1 | The Workshop Meeting. | 597 |
Figure E2 | The Control Meeting. | 599 |
Figure E3 | The Meeting Minutes. | 601 |
Figure E4 | Examples of Collaborative Behavior. | 603 |
Figure E5 | A Model for Teambuilding. | 605 |
Figure E6 | Teamwork Issues. | 605 |
Figure E7 | Obstacles in the Group. | 606 |
Figure E8 | Evaluating the Culture in the Project Group. | 607 |
Figure E9 | Analyzing the Behavior of the Participants During a Meeting. | 608 |
Figure E10 | Characterizing the Disagreement. | 610 |
Figure E11 | Reasons for Emotional Tension. | 611 |
Figure E12 | Types of Behavior in a Conflict Situation. | 612 |
Figure E13 | Reactions to a Conflict Situation. | 613 |
Figure E14 | Levels of Power in a Collaboration. | 614 |
Figure E15 | Political Activities to Gain Influence. | 615 |
Figure E16 | A Decision Model. | 617 |
Figure E17 | Advice on Decision Processes. | 619 |
Figure E18 | Activities in a Decision Process. | 621 |
Figure E19 | Preparing for a Decision. | 622 |
Figure E20 | Participants’ Possibilities of Gaining Influence. | 622 |
Figure E21 | A Model for Time-out Reflections. | 633 |
Figure E22 | An Example of a Cause-effect Analysis. | 634 |
Figure E23 | Cues for Evaluation During the Project. | 635 |
Figure E24 | A Method for Reflecting on Management Situations. | 636 |
Appendix F | ||
Figure F1 | Project Leader’s Five Management Areas. | 644 |
Figure F2 | The Project Leader’s Roles. | 645 |
Figure F3 | Checklist for Selection of a Project Leader. | 647 |
Figure F4 | Challenges for Leading the Team. | 648 |
Figure F5 | Delegation of Tasks. | 649 |
Figure F6 | Leading in a Political Milieu. | 650 |
Figure F7 | Project Manager’s Contract. | 651 |
Figure F8 | Competencies in Project Management. | 654 |
Figure F9 | Competency Elements of Leadership Behavior. | 656 |
Figure F10 | Workshop about Project Manager’s Competency Profile. | 657 |
Figure F11 | Example of a Competency Profile Form. | 658 |
Figure F12 | The Managerial Grid. | 660 |
Figure F13 | Dulewitz and Higgs Company Model. | 663 |
Figure F14 | Project Leader’s Plan. | 666 |
Figure F15 | Management of a Small Project. | 666 |
Figure F16 | Plan for Own Work. | 667 |
Figure F17 | Week Plan. | 668 |
Appendix G | ||
Figure G1 | Work Plan Form. | 671 |
Figure G2 | Example of Project Planning Billboard. | 671 |
Figure G3 | Conditions Determining Activity Duration. | 675 |
Figure G4 | Estimating Activity Duration – Three Estimates. | 676 |
Figure G5 | Principles of the Critical Chain Method. | 678 |
Figure G6 | Principles for Time Schedules in Gantt Charts. | 679 |
Figure G7 | Elements in a Gantt Chart. | 680 |
Figure G8 | Example of a Master Plan as a Gantt Chart. | 681 |
Figure G9 | Example of a Cyclogram. | 682 |
Figure G10 | Example of Network Plans. | 686 |
Figure G11 | Rules for Activity Overlap. | 687 |
Figure G12 | Time Calculation in Process Diagram. | 688 |
Figure G13 | Project Info-Room. | 690 |
Figure G14 | Info-Room Facilities. | 692 |
Figure G15 | Issue Management. | 695 |
Figure G16 | Example of the Structure of a Technical Logbook. | 696 |
Figure G17 | Work Status in a Gantt Chart. | 699 |
Figure G18 | Deadline Trend Diagram. | 701 |
Figure G19 | Basic Elements of the Progress Curve. | 702 |
Figure G20 | Example of the Line of Balance Tool (a) and (b). | 703 |
Figure G21 | Basic Elements of PMS. | 708 |
Figure G22 | The Five-by-Five Model as a Scorecard. | 713 |
Figure G23 | A Scorecard Example. | 714 |
Figure G24 | Factors Influencing Resource Consumption. | 717 |
Figure G25 | A Resource Planning Form for a Participant. | 719 |
Figure G26 | Formulas in Successive Calculation. | 723 |
Figure G27 | Example of Successive Calculation. | 724 |
Figure G28 | Timeline for Cost Control Actions. | 726 |
Figure G29 | Cost Control Activities. | 728 |
Figure G30 | Cost Summary Take in Figure. | 729 |
Figure G31 | Project Account. | 730 |
Figure G32 | Types of Deliveries and Services. | 734 |
Figure G33 | Typical Contract Elements. | 737 |
Figure G34 | Example of a Hierarchical Influence Diagram. | 739 |
Figure G35 | Example of an Influence Diagram. | 740 |
Figure G36 | Example of a Goal-Means tree for a Hydro Power Project. | 740 |
Figure G37 | Example of an Ovalogram. | 742 |
Figure G38 | Symbols and Drawing Rules for an Ovalogram. | 743 |
Figure G39 | Example of a Cause-Effect Diagram. | 744 |
Figure G40 | Symbols in a Cause-Effect Diagram. | 744 |
Figure G41 | Example of a Problem Matrix. | 745 |
Figure G42 | Example of a Gap Analysis. | 745 |
Figure G43 | Example of a Function Tree. | 746 |
Figure G44 | Description of the Development Task. | 747 |
Figure G45 | Example of a Systems Hierarchy. | 749 |
Figure G46 | A Black-Box Description of a System. | 750 |
Figure G47 | Illustration of Systems. | 751 |
Figure G48 | Description of a System. | 752 |
Figure G49 | Logical Framework Example. | 753 |
Figure G50 | Activity-Oriented and Goal-Oriented Planning. | 755 |
Figure G51 | Example of Content in the System Specification. | 760 |
Figure G52 | Content in a Basic Product Specification. | 761 |
Figure G53 | The Road to Quality. | 762 |
Figure G54 | Quality Management Activities. | 762 |
Figure G55 | Quality Assurance Plan. | 763 |
Figure G56 | A Review Procedure. | 765 |
Figure G57 | The Requirement Picture in QFD. | 767 |
Figure G58 | Example of Requirements in QFD. | 768 |
Figure G59 | Form for FMEA Analysis. | 774 |
Figure G60 | Example of Types of Changes. | 777 |
About the Book
Professional projects are increasingly confronted by complexity and ambiguity. For successful project management, it is essential to understand the project environment, business, and organizational perspectives, and to identify and interact with stakeholders. Much of the training and teaching of project management is dominated by a belief in prescribed solutions and courses of action that fit all situations, but in order to cope with the challenges of modern projects, a more holistic approach is needed.
Project Management – A Multi-Perspective Leadership Framework suggests that managers view change as an integral part of project development, allowing leaders to better adapt to difficulties and incorporate multiple perspectives. Often, public and private projects do not lead to expected success because of insufficient management of organizational change. This book presents a circular planning process, taking the reader from the loose ideas of a project’s inception through to its gradual coherence with the demands of the environment. It breaks a project down into five key elements, allowing managers to easily develop appropriate strategies. This is reflected in the broad spectrum of tools presented in the second part of the book, focusing on practical methods for both planning and leadership.
The book is targeted at practitioners who need an overview of project management techniques through a comprehensive framework and to graduate students who work with complex projects or who wish to relate their studies to broader corporate strategy.
Preface
Although project management is a rather new subject in management and organization theory, it has undergone significant developments in the last two or three decades, partly due to its widespread applications in almost all areas of society. The role of the project manager has changed from that of a planner to the role of a business developer.
For many years we have been interested in understanding the nature of the project environment, e.g., how to identify the kind and extent of uncertainties and ambiguity, how to come to grips with various kinds of complexity, and how to understand the political environment by asking who would like to see the project carried out, and who would be against it.
In recent years, this approach has been supported by new developments. For example, Agile Project Management has acknowledged that often no clear objectives of a project can be established in the early stages; rather a learning process should be staged in a dialog with customers and by means of a series of prototypes.
Lean Thinking has successfully been applied to production, service and product development with its focus on creation of value. This has also implications for project management to focus on creating effect in the receiving organization, and to ensure that stakeholders see the project as a success.
Rethinking project management has gained momentum in recent years. The starting point was an observation that a major part of the project management theory and practice was preoccupied with looking inwards to planning, organizing, and controlling of a project, rather than viewing a project in a larger context. For example, the Rethinking literature views a project as part of a strategic effort, and acknowledges the necessary organizational changes to take place in order to assure implementation of the project.
Our approach embraces these approaches and seeks to contribute to their further development by means of frameworks, models, and solutions.
We shall present five generic elements of a project, respectively, project management, project task, stakeholders (interested parties), resources, and project environment. This five-by-five model is used to identify the nature of a specific project and to develop appropriate approaches and means. It also allows a circular planning process that gradually leads to coherence among the five elements.
To better cope with the complexity of the project environment, this book adopts a multi-perspective framework by introducing four perspectives: a technical, a business, an organizational, and a stakeholder perspective. In this way, project management may be tied to corporate strategy and organizational development. Also, five dimensions of complexity will be identified and a number of means of managing complex situations will be presented.
In view of the diversity of projects, we have identified five generic types of projects, each with specific characteristics and practice. This has also led us to square up with a standard project phase model. In practice, we see numerous courses of action that reflect the specific situation of projects and that have been acted upon with great empathy and ingenuity. Instead of proposing a standard model for a project’s course of action, we will present a spectrum of different models to support a situational approach.
The increased prevalence of projects has created a need to view several projects together. Therefore, we have written a separate chapter on management of several projects, with coordination of projects in a portfolio and a program as a central theme. Also, projects’ role in corporate strategy is discussed. The chapter rests, among other things, on a survey and a development project that we have carried out in Danish companies.
The book is organized in two, almost equal parts: (1) a theoretical part covering key models and issues related to project management. The first part of each chapter introduces a few basic models to the subject of the chapter. The latter part elaborates on the subject by means of additional models and discussions. (2) Appendices with a number of tool sheets aimed at providing practical methods, techniques, and checklists associated with themes of the chapters.
This book is aimed at two groups of readers:
Graduate students who work with complex projects in their studies and who want to adopt a broader view of project management. They may be inspired by examples from practice and exercises.
Practicing and reflecting project managers who want to go beyond a specific project manual, to obtain an overview by means of a comprehensive and unified framework, and to be inspired to develop own solutions. Learning from own experience may be stimulated by reflecting on own practice in relation to general models and relevant tools. It may be supported by keeping a logbook with weekly descriptions of activities, important decisions and incidents. Mutual learning may be facilitated by forming an experience group of project managers.
It will require empathy, intuition, creativity, and interplay with people to work with projects on the basis of an effort to understand the project environment, including the uncertainty and complexity of the project task. This will make project management more challenging and also more interesting and rewarding. It may be relevant to ask if companies and institutions are willing to support a more situational, task-oriented and value-driven mode of working with projects, rather than focusing on complying with procedures and directions. We believe that a more systematic and explicit delineation of the project conditions and a broad discussion of the project task will make it possible to clearly define the responsibilities of a project.
Often in the book, we use the term ‘company’ as the place where projects take place. It should be interpreted in a broad sense to include private and public companies, public institutions and administrations, as well as networks of organizations.
We are indebted to Ms. Anna Falcon Svendsen for her great effort to format our manuscript and figures into a readable form, and to Ms. Louise Olesen Kragh for editing our English manuscript and Ms. Kirstine Rosenkrands Mikkelsen for translation assistance. We thank Annette Wier for her vignettes. We would also like to thank Jaya Chowdhury (MPS Limited, Chennai, India), the Project Manager of our book.
Hans Mikkelsen
Jens O. Riis
April 2017
- Prelims
- 1 Introduction
- 2 Forming and Defining the Project
- 3 Planning the Course of Action
- 4 Organizing
- 5 Cooperation in the Project Organization
- 6 Project Leadership
- 7 Project Control
- 8 Management of Several Projects
- 9 Trends and Challenges for Future Projects
- Appendix A: Project Characteristics
- Appendix B: Forming and Defining the Project
- Appendix C: Planning the Course of Action
- Appendix D: Organizing
- Appendix E: Cooperation in the Project Organization
- Appendix F: Project Leadership
- Appendix G: Project Control
- References
- About the Authors
- Index