An Opposite Design-Build Procurement Method: Competing on Quality with a Fixed Price

Leif D. Houck (Faculty of Science and Technology, University of Life Sciences, Ås, Norway)

10th Nordic Conference on Construction Economics and Organization

eISBN: 978-1-83867-051-1

ISSN: 2516-2853

Publication date: 1 May 2019

Abstract

Purpose

For a public project leader charged with a construction project, it can be crucial to meet the budget, while maximizing the qualities within a construction project. A method to achieve this is to use the “opposite design build” procurement method, in which the price is fixed and the contractors compete on adding a wide range of qualities to the project. However, such procurement approaches are rare, and it is difficult to find models on how to implement such an approach.

Design/Methodology/Approach

This study firstly looks at the literature on design-build, quality-only as the main selection criterion and to some degree on constructors’ bidding behaviour. Secondly, it explains a model for a design-build, quality-only procurement designed within the public tendering legislations. Thirdly, it investigates the outcome of the model applied to a specific case in Norway.

Findings

There seems to be a research gap within literature and cases on design-build, quality-only selection with a fixed price. The developed model allowed for negotiations, which led to more comparable and improved bids. In the investigated case, and the client was able to implement more qualities in the project than expected within the budget.

Research Limitations/Implications

The researcher was himself partly involved in the process as an advisor.

Practical Implications

The developed method is relatively simple and might readily be applied by any client to maximise a project’s qualities within a given fixed price.

Originality/Value

The long-term value should be to widen the range of useful procurement methods.

Keywords

Citation

Houck, L.D. (2019), "An Opposite Design-Build Procurement Method: Competing on Quality with a Fixed Price", Lill, I. and Witt, E. (Ed.) 10th Nordic Conference on Construction Economics and Organization (Emerald Reach Proceedings Series, Vol. 2), Emerald Publishing Limited, Leeds, pp. 93-100. https://doi.org/10.1108/S2516-285320190000002015

Publisher

:

Emerald Publishing Limited

Copyright © 2019, Leif D. Houck.

License

Published in the Emerald Reach Proceedings Series. Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode


1. Introduction

For a public project leader charged with a construction project, it can be crucial to meet the budget, and at the same time maximize the qualities within a construction project. One method to achieve this is to use the “opposite design build” procurement method, where the price is fixed, and the competitors compete on delivering qualities. This study firstly examines some of the literature on design-build, quality-only as the dominant selection criterion, and to some degree the constructors’ bidding behaviour. Secondly, it explains a model for a design-build, quality-only procurement. Thirdly, it investigates the outcome of the model applied as applied to a specific case.

The case project is a public nursing home project consisting of five two-storey buildings with a total built areas of 3,300 m2 located in Hammerfest, a small town in the north of Norway. In this case, the author of this paper was asked for advice on what procurement method to use. Often public owners select the procurement routes they are in the habit of (Lædre et al., 2006), but this particular client had an open-minded approach. The municipality had decided on a budget for the project, and this sum became common knowledge through the public budget of the municipality. The client was concerned that the contractors would perhaps quote a price on the project based on their pre-knowledge of the budget sum, and less on the actual tendering documents. There also was a concern that the bids would exceed the building costs allowed for within the project’s budget. And not least there was a clear wish to maximize the qualities in the project without exceeding the costs set in the budget. It was then decided to go for a procurement method with a fixed total cost, and where the contractors should compete in terms of improving the quality of the project, in Norwegian terminology called “opposite design-built” procurement. However, as we could not find any specific model or case for this procurement method, a model had to be developed. The tender documents were published in January 2017, and the contract was signed during spring 2017, with delivery early in January 2019.

2. Research Method

The methods used are a literature study, a document study and interviews. A literature study was executed using Google Scholar, Worldwidescience, Oria and Citation Chaining (Ellis, 2015). Norwegian, Swedish, Danish, English and German terms were used. Examples of the English searches are: “procurement type construction”, “construction procurement overview”, “Design-Build fixed price”. Actual cases were searched for on Google. The client allowed the author to examine the Excel data pages containing the cost information for the respective bids, and the client’s assessments of these. Additionally, the project manager, the project leader and four contractors were interviewed on phone. Emails were sent back and forth to verify various details. In this paper, the author has assumed several different roles: one role has been as the co-owner of the architectural firm responsible for submitting the preliminary design. The second role was as the advisor in the matter of recommending a procurement method, creating the procurement model and working out the tendering documents. A third role is being the author of this paper and in that sense a researcher in a case where the author has worked as a key participant. After the tendering was published, the author has not participated in any further activities, such as negotiations or evaluations.

3. Theory and literature

3.1. Design-build, selection methods and pricing

There is an extensive amount of literature describing design-build procurement, its definition, benefits and challenges. In literature dating back to 2000-2007, design-build is often referred to as not only one of the more “new procurement methods”, but also “rise of an old project delivery method” (Pietroforte and Miller 2002). After some experimenting starting in the USA in 1968, the Federal Acquisition Regulations were modified to include regulations for design-build in 1997 (Beard et al., 2001). Rahmani et al. describes design-build as an integrated method using a single contractor to act as the sole point of responsibility normally on a lump sum fixed price basis (Rahmani et al., 2017). In German and Austrian literature, design-build is commonly referred to as new “Angloamerican” methods (Thomas, 2008). A design-build procurement with a lump sum contract could be translated into German as a “Wettbewerbsform Gesamtübertragung” with “Globalpauschalvertrag” (Gralla, 2001) or “Komplexer Global-Pauschalvertrag (Kapellmann, 2017). The design-build arrangement is attractive for clients owing to the single-point responsibility, prices reflecting the final cost, more buildable designs and an overlap of design and construction phases leading to early completion (Brook, 2017). Songer and Molenaar (1996) identify seven selection factors making owners select design-build as a delivery strategy. Among these are securing costs, decreasing the overall project costs, shortening the duration and introducing construction knowledge into design early in the process.

Less literature was found describing the selection methods for awarding a contractor in design-build procurement, but there are some (Beard et al., 2001, Songer and Molenaar, 1996, Gordon, 1994). For public clients, mainly three methods are pointed out, namely, lowest price, highest quality or performance or a combination of the two. Some literature additionally describes the qualification based selection method (Wardani et al., 2006). In European tendering legislation terminology, the expression “most economically advantageous tender” (MEAT) describes the selection method of combining quality and price. Authorities are permitted to determine MEAT on the basis of quality alone (Brook, 2017). Other terms for describing the quality-only selection method, are “Stipulated sum/best design” (Beard et al., 2001) and “cap”, which is defined as a fixed price against which contractors propose a level of quality and options for a project (Gordon, 1994). Bergman and Lundberg (2013) discuss the selection methods intensively and argue that “quality-only scoring may be the best method when funds are earmarked for a particular project”. While some literature investigates methods to combine the price and quality selection method, there seems to be a research gap related to design-build procurements using quality only as the dominant award criterion.

The Norwegian Agency for Public Management and eGovernment, DIFI, describes the term “opposite design-built” (Omvendt totalentreprise) as a procurement method where the project’s maximum cost is defined and the bidders compete in offering lower bids than the maximum cost set by the client. One problem with this definition is that the price ends up not being fixed, and quality aspects are not included. In Denmark, the term “opposite design-built” (omvendt-licitation) is described as a design-build tendering at a fixed price, or a target price where the contractors compete on how to meet the client’s demands in the best possible way (Danske Regioner, 2015). This could mean either higher quality or more square meters being constructed. In Denmark, this seems to be a rather commonly used procurement method, and is frequently mentioned on relevant websites as in newspapers and informational material (Konkurrence og Forbrugerstyrelsen, Aktivitetsrum.dk, 2015). In this paper, the term “opposite design-build” procurement should be understood as basically in accordance with the Danish definition, but more specifically as a design-build with a fixed price and quality as the dominant award criterion.

When competing on price, opportunistic bidding behaviour is frequently observed, often resulting in cutting corners and claims (Lo et al., 2007). Quality-based selection systems have a potential to encourage contractors to place more emphasis on project quality (Wardani et al., 2006). The success of the quality-based selection system is strongly dependent on also evaluating the contractors’ past performance and the evaluation of contractors’ qualifications. When it comes to the calculation of the bid itself, Brook (2017) describes top-down estimating as meeting and improving on a client’s target price for a project. Bottom-up estimating is characterised by creating a bill of quantities and work packages based on a design solution.

3.2 Public procurements and negotiations

As a member of the European Economic Area (EEA), Norway’s public procurement laws and regulations are obligated to be in accordance with the EU legislations. New EU Directives on public procurement, 2014/23-25/EU, resulted in new laws and regulations in Norway from 1 January 2017 (Gusvik and Werner, 2018). For projects with an estimated cost above the EU threshold, the Norwegian Public Procurement Act (Nærings-og fiskeridepartementet, 2017) only allows for negotiation if the task cannot be described clearly or if the project is of a certain complexity. In Denmark, the so called “client association” (Bygherre Foreningen) states that negotiations can be used in design-build procurements where quality is used as competition criterion (Bygherre Foreningen, 2016). Eriksen and Hane (2014) emphasise the importance of using the possibility to negotiate. The aim of the negotiations is to address misunderstandings, mistakes, reservations and possible improvements. Through the negotiation process, the client receives more comparable and improved bids (Burnett and Oder, 2015, Beard et al., 2001). Any relevant part of the contract can be subject to negotiation. Such legislated limitations on allowing for negotiations result in a low number of negotiated procurements in most EU-countries. Analysis of data received from the Norwegian Agency for Public Management and eGovernment (Difi) reveals that of a total 332 public procurements with the CPV code 45 construction works in 2017, only 1 per cent were negotiated procedures. In 2016, their amount of negotiated procedures was 4 per cent. In Sweden, 8.6 per cent of the construction related contracts followed a negotiated procedure in 2013 (Lukkarinen and Jönsson, 2015). Interestingly, from April 2010 to March 2011, the corresponding statistics for France and the United Kingdom were 43.7 per cent and 34.4 per cent, respectively (Burnett and Oder, 2015). Despite the same legal framework, a client wanting negotiations in Norway seems to have to pass through the eye of a needle.

4. The Opposite Design-Build Procurement Model in the case study

The concept was to write a “minimum” description and a list of pre-defined additional qualities that the contractors should compete on offering within a fixed price. The client was of the opinion they had the competence for deciding the fixed price. It should not be set too high as this would result in an expensive project, although not too low as that might discourage the contractors from bidding. The fixed price was set to be NOK 70m, which is above the EU threshold of NOK 44m. According to the Procurement Regulations, open procedure or restricted procedure without negotiations should be used as a main rule. However, the client saw a great advantage in being able to negotiate. Therefore, the approach was discussed with the solicitor, a well-known expert on procurement contracts. The solicitor put forth the argument that as the competitors would be competing on quality, the regulations would allow for negotiations. The solicitor reasoned that competing on quality made the procurement sufficiently complex.

The tender consisted of preliminary building designs, a description of the wanted functions and performances, and quality requirements. The quality level of the project was set to a reasonable minimum, good enough to satisfy the project’s basic functions and proposed use. A list of 19 additional diverse qualities was developed. Examples given were tiles on bathroom walls, wooden slatted ceilings in shared spaces, replacing gypsum walls with fibre–gypsum walls, wooden slatted niches at apartment entrances, plywood pattress behind gypsum walls in kitchens and living rooms, SD control system for ventilation, fulfilling the Low Energy Standard NS3700:2010, the use of Environmental Product Declarations (EPDs) and the use of BIM-collision tests during the planning phase. Additionally, the contractors could suggest other quality improvements themselves.

The award criteria and weighting were set as follow in the tendering documents (the regulations allow for the use of intervals):

  • Added quality – offered qualities from the quality list, 60–70 per cent

  • Comprehension of assignment and experience level, 20–30 per cent

  • Cost (labour rates and material costs for any potential additional work/alterations) 10 per cent

The tender documents described that the contractors had to quote a set price for every quality on the quality list, and to offer a sum, or an “economic scope of action” for the client to “shop” qualities within the fixed price. By doing so, the client did not have to decide in advance what qualities he would prioritise. Also, the client was at liberty to make these priorities after seeing the level of cost of the respective qualities. The system for ranking would be to pick the contractor with the most advantageous scope of action in relation to the wanted combination of qualities.

Section headings within the body text should be numbered sequentially. The wording of headings is at the discretion of the authors.

5. Results and discussion

All contractors submitted bids within the fixed sum of NOK 70m. As seen in Figure 1, Contractor Three offered no added qualities, and Contractor Four included all qualities in the bid. The pricing of the added qualities does not necessarily reflect the actual cost of the respective qualities, such as prices, are subject to competition and may thus also represent strategic pricing.

Figure 1: 
Quality costs before negotiations. (Dark columns: the respective total cost for all the qualities; white columns: the respective offered ‘scope of action’ that the client could spend on added qualities within the fixed price)

Figure 1:

Quality costs before negotiations. (Dark columns: the respective total cost for all the qualities; white columns: the respective offered ‘scope of action’ that the client could spend on added qualities within the fixed price)

The final weighing of the award criteria was decided during the evaluation (see Table 1). The negotiations were executed by a three-person team from the client’s project and procurement department. The negotiations were handled through email. Some bids were lacking in information or there had been some misunderstandings and miscalculations, and one contractor had reservations in the bid, which should not be the case and therefore had to be priced. The contractors were told indicatively whether their bids were high or low compared to the other bidders. But all bidders were also told they were in position to win. The negotiations led to more comparable bids with improved performances on quality.

Table 1:

The competitors’ final scores

Criterion/Contractor 1 2 3 4 5
1. Quality (60%) 59.81 59.9 53.5 60 57.8
2. Comprehension of assignment (30%) 30 29,4 27 27 26.1
3. Cost (10%) 9.74 9.22 10 9.2 9.19
Total 99.55 98.5 90.5 96.2 93.1

Contractor One made the most significant change in their bid after the negotiation. The contractor simply more than halved the total cost of the qualities with the result that all the qualities on the quality list were implemented in the bid. Additionally, Contractor One was considered to have the best comprehension of assignment and therefore won the competition.

The client regarded the opposite design-build method as successful. Owing to the dominant weighting of the quality award criterion, combined with negotiations, the client was able to implement the total list of technical, material and performance qualities within the fixed price. As shown above, the Public Procurement Act is very restricted in allowing negotiation for contracts above the EU threshold. Therefore, a client could consider using the opposite design-build as a method for enabling negotiation. However, other legal experts may come to conclusions other than what the expert arrived at in this project. It is debatable whether the task is sufficiently complex to defend the use of negotiations in this model. What speaks for the use of negotiations as applied in this procurement are the recommendations in the literature (Erikson and Hane, 2014), and the fact that negotiations are rarely used in Norway comparable to other coutries with the same legal framework. In addition, one might also argue that the given method is transparent, as the qualities are pre-defined and measured in cost. The complexity in the evaluation lies primarily in the choosing of the specific additional qualities when the costs, and therefore the scope of action, are known. In this case, two bidders offered all qualities, but if this had not been the case, a more complex evaluation of each quality’s value compared to cost would have been necessary.

One risk involved with this model, however, is to decide the level of the fixed cost. As two of five bidders in this case offered all qualities after negotiation, the fixed price could be considered a fair fixed price. But what if there would be no bids because the fixed price was set to low? The client had no concern for such a scenario. If it had been the case that no contractors would deliver any bids, then the Public Procurement Act would have allowed the client to contact some of the qualified contractors and negotiate directly with them. The client did not consider this type of scenario as necessarily disadvantageous.

All the interviewed contractors generally, as in this case, used a detailed bottom–up method to calculate the price. Eventually, they would compare this bottom-up calculation to the municipality’s published project cost. Any adjustments would probably be downwards as the contractors were of the opinion that the municipalities generally had too low budgets. One of the contractors was critical towards other selection criteria than lowest price, as e.g. “comprehension of assignment” was not considered transparent. Lastly, all contractors argued that prices were kept low owing to heavy competition.

6. Conclusions

According to the literature search, the opposite design build-procurement method seems to be more established in Denmark than any other countries investigated. Also the literature study shows a research gap concerning the opposite design-build method. The procurement method, as outlined above, showed to be a useful tool for upgrading the quality of the project within the given budget, which is in accordance with Bergman and Lundberg (2013). The argument for using fixed price to help prevent contractors from quoting the municipal budgets seems weak. The method worked well within the existing bidding culture and contracting standards. The procurement method allowed the client to maximise the project qualities within the budget, while allowing the client and contractors to take advantage of the negotiations. The method does, however, require a solid knowledge of the local cost level for the specific building type.

References

Aktivitetsrum.dk, Totalentreprise, 2005Aktivitetsrum.dk. Totalentreprise. (2005) [cited 2018 04.04]; Available from: http://aktivitetsrum.dk/t2w_617.asp

Beard, Loukakis, Wundram, 2001Beard, J. L., Loukakis, M. C., Wundram, E. C., (2001) Design-build: Planning through development. New York: McGraw-Hill.

Bergman, and Lundberg, 2013Bergman, M. A. and S. Lundberg, (2013) Tender evalutation and supplier selection methods in public procurment. Journal of Phurcasing & Supply Management, 2013. 19.

Brook, 2017Brook, M., (2017) Estimating and Tendering for Construction Work. 5 ed., Abingdon, Oxon. New York: Routledge.

Burnett, and Oder, 2015Burnett, M. and Oder, M., (2015) Competitive Dialogue and Negotiated Procedures. A Practical Guide. 2 ed., Maastricht, Netherlands: EIPA. European Institute of Public Administration.

Bygherre_Foreningen, 2016Bygherre_Foreningen, (2016) Drejebog for bygherrer - Udbud med forhandling. Bygherre Foreningen.

Danske-Regioner, 2015Danske-Regioner, (2015) Vejledning udbudsstrategi. Danske Regioner: Denmark.

Ellis, 1993Ellis, D., (1993) Modeling the Information-Seeking Patterns of Academic Researchers: A Grounded Theory Approach. The Library Quarterly, 1993. 63(4).

Erikson, and Hane, 2014Erikson, P. E. and Hane, J. (2014) Entreprenadupphandlingar, S.C. Authority, Editor. Sweden.

Gordon, 1994Gordon, C. M., (1994) Choosing Appropriate Construction Contracting Method. Journal of Construction Engineering and Management, 1994.

Gralla, 2001Gralla, M., (2001) Garantierter Maximalpreis. Leitfaden der Bauwirtschaft und des Baubetriebs, ed. F. B. B. Kochendörfer. Germany: Teubner.

Gusvik, and Werner, 2018Gusvik, A. and Werner, L. C. (2018) Public Procurement 2018 - Norway. [cited 2018 23.3.2018]; Available from: https://iclg.com/practice-areas/public-procurement-laws-and-regulations/norway.

Kapellmann, 2013Kapellmann, K. D., (2013) Schlüsselfertiges Bauen. Düsseldorft, Germany: Werner Verlag.

Konkurrence-_og_Forbrugerstyrelsen, 2008Konkurrence-_og_Forbrugerstyrelsen, (2008) Guide- Bygherrens indkøbs- og udbudsstrategier - for bedre konkurrence i bygge- og anlægssektoren, K. Bygherreforeningen, Editor. Konkurencestyrelsen; Bygherreforeningen: København.

Konkurrence-_og_Forbrugerstyrelsen, 2016Konkurrence-_og_Forbrugerstyrelsen. (2016) Hvordan foregår en omvendt licitation? [cited 2018 04.04]; Available from: https://www.kfst.dk/faq/udbud/nyt-udbud/fase-1/hvordan-foregaar-en-omvendt-licitation/.

Lo, Lin, and Yan, 2007Lo, W., Lin, C.L., and Yan, M. R. (2007) Contractor’s Opportunistic Bidding Behaviour and Equilibrium Price Level in the Construction Market. Journal of Construction Engineering and Management, 2007.

Lukkarinen, and Jönsson, 2014Lukkarinen, J. and Jönsson, S. (2014) Siffror och fakta om offentlig upphandling. Konkurrensverket - Swedish Competition Authority: Stockholm.

Lædre, Austeng, Haugen, Klakegg, 2006Lædre, O., Austeng, K., Haugen, T., Klakegg, O. J., (2006) Procurement Routes in Public Building and Construction Projects, Journal of Construction Engineering and Management,2006. 132(7)

Nærings-_og_fiskeridepartementet, 2017Nærings-_og_fiskeridepartementet, (2017) Forskrift om offentlige anskaffelser (anskaffelsesforskriften), N.-o. fiskeridepartementet, Editor. 2017, Lovdata.

Pietroforte, and Miller, 2002Pietroforte, R. and Miller, J. B., (2002) Procurement Methods for US Infrastructure: Historical Perspectives and Recent Trends. Building Research & Information, 2002. 30(6).

Rahmani, Maqsood, Khalfan,2017Rahmani, F., Maqsood, T., Khalfan, M.,(2017) An Overview of Construction Procurement Methods in Australia. Engineering, Construction and Architectural Management, 2017.

Songer, and Molenaar, 1996Songer, A. D. and Molenaar, K. R., (1996) Selecting Design-Build: Public and Private Sector Owner Attitudes. Journal of Management in Engineering, 1996.

Thomas, 2008Thomas, M., (2008) Neue Projektabwicklungs- und Bauvertragsmodelle. Theorie, Utopie unde Wirklichkeit, in 3. PM-Bau Symposium. 2008: Austria.

El Wardani, Messner, Horman, 2006El Wardani, M. A., Messner, J. I., Horman, M. J., (2006) Comparing Procurement Methods for Design-Build Projects. Journal of Construction Engineering and Management, 2006.

Håkon Rønbeck, Hammerfest Kommune, Norway

Prelims
THE ECONOMICS AND BUSINESS OF CONSTRUCTION
Updating and Cleaning Out: The “Make or Buy” Decision in Construction Revisited
Bispevika Project: Research for Constructing a Collaborative Value Chain
Social Considerations in the Procurement of Road and Railroad Projects in Sweden
Standardization and Industrialized Construction of Special Purpose Building
Identifying Contradictions of Integrating Life-Cycle Costing in Design Practices
Advancing Networking-Based Business Management in Construction Markets
Contracts and Culture in a Partnering Project
Sub-Contractors’ Perception of Contracting: The Case of Crime
Project Managers: Gatekeepers or Inside Men?
The Hybridity of Strategic Partnerships and Construction Supply Chain Management
Dynamic Capabilities and Risk Management: Evaluating the CDRM Model for Clients
An Opposite Design-Build Procurement Method: Competing on Quality with a Fixed Price
CONSTRUCTION AND PROJECT MANAGEMENT
An Appraisal of Water Infrastructure Projects’ Financing Challenges in South Africa
The Soft Factors in Design Management: a Hidden Success Factor?
Room to Manoeuvre: Governing the Project Provisions
A Longitudinal View of Adopting Project Alliancing: Case Finland
A Simulation-Based Optimization for Contractors in Precast Concrete Projects
Governed by Municipal Land Allocations: Implications for Housing Developers
Situation Picture Through Construction Information Management
Who Benefit from Crime in Construction? A Structural Analysis
Quality Evaluation of Contractor’s Schedule in the Bidding Phase
Activity Cruciality as Measure of Network Schedule Structure Resilience
Construction Programmes and Programming: A Critical Review
Procurement Research: Current State and Future Challenges in the Nordic Countries
Exploitative Learning in Inter-Organizational Projects: Evidence from Dutch Infrastructure Practices
The Transition from Design-Bid-Build Contracts to Design-Build
Exploring the Dynamics of Supplier Innovation Diffusion
Understanding Collaborative Working in a Facilitated Interdisciplinary Environment
Ensuring Successful Knowledge Transfer in Building Renovation Projects
Public Private Collaboration in the Context of Zero Emission Neighbourhood
Strategizing and Project Management in Construction Projects: An Exploratory Literature Review
BUILDING INFORMATION, DATA AND DIGITALIZATION
BIM-Enabled Education: a Systematic Literature Review
A BIM-Enabled Learning Environment: a Conceptual Framework
“I Work All Day with Automation in Construction: I am a Sociomaterial-Designer”
Developing Smart Services to Smart Campus
An Overview of BIM Adoption in the Construction Industry: Benefits and Barriers
BIM for Construction Education: Initial Findings from a Literature Review
Model for Smart, Self-learning and Adaptive Resilience Building
Investigating the Drop-Out rate from a BIM Course
INNOVATIONS IN THE CONSTRUCTION PROCESS
Senior Residence Concepts in Norway: Challenges and Actions for a Sustainable Development
3D-Printing Technology in Construction: Results from a Survey
Product and Manufacturing Systems Alignment: a Case Study in the Timber House Building Industry
Opening the Black Box of Accessibility Regulation
Orchestrating Multi-Actor Collaborative Innovation Across Organizational Boundaries
SUSTAINABILITY AND RESOURCE EFFICIENCY
Social Sustainability in Modelling of Value Creation in Housing Refurbishment
Reviewing the Role of Sustainability Professionals in Construction
Exploring the Evolution and Impact of Building Environment Assessment Methods in Achieving Green Building
STAKEHOLDERS OF CONSTRUCTION AND REAL ESTATE
Challenging the Rhetoric of Construction Briefing: Insights from a Formula 1 Sports Venue
Underlying Causes for Risk Taking Behaviour Among Construction Workers
Towards Developing a Framework for User-Driven Innovation in Refurbishment
Reconstructing Knowledge Integration in the Norwegian AEC-Industry
Institutional Complexity for Chinese International Contractors
BUILT ENVIRONMENTS
BIM Related Innovation in Healthcare Precinct Design and Facilities Management
Location is Crucial in Retrofit: Strategy Selection in Different Regions
CONSTRUCTION EDUCATION AND RESEARCH
From Theoretical to Practical Competence on Health and Safety
A Test Platform of Viable Methods to Improve Production and Learning on Construction Sites